Services Provided: Engineering, Supply, Fob-Deliver and Erection of:  Electrical Package to Combined Stacker-Reclaimer with Intermediate Conveyor and Tripper Car –  Compagnie des Bauxites de Guinée – KAMSAR Plant – Guiné Conacry.

Project Details

Date:2013-2014
Main Contractor:Koch
Country:Guinea Conakry
Procurement:Electrical and instrumentation equipment’s, Electrical and instrumentation cables; Hearting cables; Steel supports; Cable trays;
Construction:Construction and installation activities for the total electrical and instrumentation portion of the works.Requiring 17.470 productive man hours, with 26 people at peak period. Automation Works: Development of PLC and XBT program, installation and commissioning. The machine is controlled by one PLC Premium – Schneider, 6 Remote I/O – WAGO and one HMI console for the operation with a total of 454 I/O. The communication between the PLC and the different equipments installed is preformed, by the protocols CANOPEN, and MODBUS TCP.
Installed quantities:Cable trays: 350 m Electrical cables: 4900 m Control & Instrum. Cable: 3900 m Instruments: 80 items LV panels: 3 units Lighting : 52 units