Service Provided: Procurement, erection, pre-commissioning, for instrumentation works for the biggest Europe Paper Mill Plant.

Project Details

Date:2008 - 2009
Main Contractor:ATF
Country:Portugal
Procurement:Procurement of the bulk material, and itemised equipment such as cables, junction boxes, cable trays, hook-ups material
Construction:Construction and installation activities for the total instrumentation portion of the works requiring 106 000 productive man hours with 160 people at peak period
Installed quantities:Cable trays: 12 000 m Junction boxes: 65 units Instrument cables: 110 000 m Instruments: 2 920 items