Services Provided: Cable Pulling, cable connection, JB installation, Panels installation, wiring, grounding, hook-up, cable tray installation, PB system, tests.on the Steam Reformer, at Sines Refinery

Project Details

Date:2010 -2011
Main Contractor:TECHNIP
Country:Portugal
Procurement:Procurement of the bulk material and itemised equipment such as cables, cable trays, hook-up, supports and grounding material.
Construction:Electrical and instrumentation portion of the works required 27.000 productive man x hours with 32 people at peak period
Installed quantities:Cable Trays : 3.000 m Cables : 20.000 m PB: 15 JB’s and Panels: 222 units Field instruments: 222 units