Services Provided: Engineering, erection, pre-commissioning, assistance to commissioning and start-up for the electrical and instrumentation works for a new ETAR (Waste water treatment plant) of Vila Franca de Xira

Project Details

Date:2002-2005
Main Contractor:DEGREMONT
Country:Portugal
Procurement:Procurement of the bulk material and itemized equipment such as electrical switch boards and panels, transformers, UPS’s, automates, cables, cable tray, junction boxes.
Construction:Construction and installation activities for the total electrical and instrumentation portion of the works involving 9.000 productive man x hours with 20 people at peak period.
Engineering:Basic and detailed engineering involved total of 1.500 man x hours with 5 people at the peak period
Installed quantities:Cable Trays : 1.290m Conduit: 1.250m Electrical Cables : 13.650m Instrumentation Cables : 22.650m Junction Boxes : 24 units Local Control Box: 91 units EV’s local Control Box: 14 units Earthing system (Cable installation): 1.560m Instruments: 208 units LV panels and Local panels: 10 units HV Panels: 2 units Automate Panel : 4 units Lightning Protection : 1 unit