Service Provided: Engineering, erection, pre-commissioning, assistance to commissioning and start-up for electrical and instrumentation works for a new ETA (Treatment Water Plant) Unit at Figueira da Foz city.

Project Details

Date:1996 - 1997
Main Contractor:SETAL DEGREMONT
Country:Portugal
Procurement:Procurement of the bulk material and itemised equipment such as electrical switchboards and panels, transformers, automates, cables, cable trays, junction boxes.
Construction:Construction and installation activities for the total electrical and instrumentation portion of the works requiring 7.500 productive man x hours with 15 people at peak period.
Engineering:Detailed engineering requiring a total of 1500 man x hours with 6 people at peak period.
Installed quantities: Cable trays: 800 m  Electrical cables : 24000 m  Instrumentation cables : 7000 m  Junction boxes : 20 units  Automates: 6 units  Instruments: 120 items  LV and lighting panel : 6 units  Lighting fixtures : 170 units